Rio Grande Boulevard Bike Lane Improvements

The scope of this project is to widen the roadway and provide bicycle lanes along Rio Grande Blvd from the Los Ranchos boundary to Alameda Trail. The improvements include on-street bicycle lanes, possible sidewalk improvements, roadway mill & fill, utility relocations, and improvements to the irrigation canals.

Schedule: Project is currently in the construction phase with an anticipated completion in late March, 2017. The project is being expedited in order to complete the improvements to the irrigation canal system prior to the beginning of the irrigation season on March 1.

General Project Information

Status | Construction
Project Engineer | Howard Cake, P.E.
Design Consultant | T.Y. Lin International Group
Design NTP | 09/10/2015
Contractor | Albuquerque Asphalt
Construction NTP | 01/17/17

Project Contact Information:
Howard Cake, P.E.
(505) 848-1567
hcake@bernco.gov

        

 