County-Wide Road Improvements Project, Phase 6 – Tramway Lane

Scope

This project reconstructed the asphalt paving on Tramway Lane from Tramway Blvd to Tramway Lane Court. Reconstruction included pulverization/compaction of existing asphalt surface and placement of new asphalt. Tramway Lane will remain open during construction and traffic will be controlled by flaggers in the vicinity of the construction activities.

Schedule

The project was completed in August, 2015.

General Project Information:

Status | Completed
Section| Brad Catanach, P.E.
Engineer | Frank Williams, P.E.
Design Consultant | Bernalillo County Public Works
Project % Design Completed | 100%
Construction Contractor | Star Paving Company
Estimated Construction Cost | $345,626
Project % Completed | 100%

Project Map

Project Contact Information:

Frank Williams, P.E.
(505) 848-1572
frankw@bernco.gov