Sunset Gardens Road Phase 2

Project Scope

Sunset Gardens Road Phase 2The project reconstructed Sunset Gardens Road, SW from the Arenal Acequia to Sunset Road, SW, then continued on Sunset Road SW to Trujillo Road SW, and continued east on Trujillo Road SW where it crossed an easement into the Valle Del Bosque Park.

The project constructed a new storm drainage system with curb and gutter and sidewalk. There was also an expansion to the Valle Del Bosque Park drainage pond.

General Project Information

Status | Completed
Project Engineer | Rodrigo Eichwald, P.E.
Design Consultant | Wilson & Company
Design NTP | 09/30/12
Construction NTP | July 30, 2014

Construction Contractor | New Mexico Underground Contractors, Inc.

Project Schedule | Gantt Chart

Project Map

Project Contact Information:
Rodrigo L. Eichwald, P.E.
(505) 848-1574