Paseo del Norte Access, Fire Station 35

Project Scope

This project provides roadway and signal improvements to allow emergency vehicles direct access to Paseo del Norte from county Fire Station #35, located on the Paseo del Norte frontage road between Browning and Lowell Streets. These improvements will reduce response time since emergency vehicles will no longer need to travel along the frontage road to access Paseo del Norte at Browning or Lowell Streets. 

Schedule: The design effort for this project began in May, 2014. Construction started on February 22, 2016 and was completed June 20, 2016. 

Funding: Funds in the amount of $275,000 were provided by the state Legislature.

Project Site Map
Project Schedule/Gantt Chart

General Project Information
Status | Construction
Project Engineer | Lee Engineering
Contractor | Star Paving Company
Construction Start | February 22, 2016
Project Completion | June 20, 2016
Time % Completed | 100 percent 