O48 Establish a fully operational data center and disaster recovery site (%) Government Accountability Increased Effectiveness

Action Steps

  1. Add second internet connection - Q1 FY18
    a. Procure redundant connection
    b. Configure redundant route
  2. Establish new data center at Alvarado Square - Q2 FY18
    a. Build fully operational data center
    b. Migrate data and services
    c. Establish disaster recovery functionality at secondary site
    d. Publish plans for IT data center in Alvarado Square - by 2019

Why is this measure important?

The move to Alvarado Square will require the construction and activation of a new data center. This data center will house all systems required for the continued operation of the county's public and private systems. A major milestone of this project is to use this process to establish a fully synchronized disaster recovery site. The disaster recovery site will require a secondary internet connection to allow county operations to continue should the primary data center become unavailable.

Where does the data come from?

Status updates will come from the progress toward three major milestones:

  1. The complete build out of a new data center
  2. The complete migration and synchronization of county data and IT services
  3. The go-live of the county's disaster recovery site

How is the measure calculated?

Measured by the percentage of progress - project and associated tasks will be tracked daily and updated quarterly  

Who to contact if you have questions?

IT Department

Additional Information

 


 

FY19 Target

25%

% of project complete

FY20 Target

75%

% of project complete

Trend Analysis