Barcelona Road Storm Drain Project Phase 3

Project Scope

The Barcelona Road Storm Drain Project is a tributary of the South Valley Flood Reduction Project. This project consists of road and drainage improvements for Barcelona Road from the Isleta Drain to Coors Blvd. Drainage Improvements will capture runoff and will connect to the Isleta Drain. Roadway improvements shall consist of bicycle lanes, curb and gutter, and sidewalk (on the north side of Barcelona) to provide a safe roadway corridor. This project will include the side roads in the area: Eames Road, Sylvia Road, Sylvia Place, Dover Road, La Loma Road and Hughes Road.

DESIGN Phase 3

Design Consultant | WHPacific Inc.
Design Cost | $300,000
Design Notice to Proceed | June 2019
Funding: Bernalillo County Storm Drain Bonds

Construction

Phase 3: Between Isleta Drain and Coors Boulevard
Construction Estimated Notice to Proceed | Fall 2021
Construction Estimated Cost | $4.8 million
Funding: TBD
Traffic Control Phasing: TBD

Project Contact Information:
Christi L. Tanner, P.E., Project Engineer
Office Phone (505) 848-1523
Cell Phone (505) 850-2041