Second Street Trail Phase 2, Prosperity Avenue to South of Rio Bravo

Updated April 6, 2020

Project Scope

This project will construct a 10-foot wide asphalt multi-use trail along the east side of Second Street, from Prosperity Avenue to Rio Bravo Blvd., approximately one mile. In 2016, the first phase of this project constructed the trail between the South Diversion Channel and Prosperity Ave.

This project is to start Construction April 20, 2020.

Traffic Control | Two lanes of traffic will be open.  Construction will be on the east shoulder of 2nd Street and parallel to the railroad tracks.  

General Project Information

Status | Design
Project Engineer | Christi Tanner
Design Cost | $175,407
Design Began  | March 2018
Design Completion | June 2019
Design Consultant | WSP USA Inc.

Construction Start | April 20, 2020

Construction End | August 20, 2020
Construction Cost | $992,940.00
Funding | Construction will be funded with Bernalillo County Road and Trail Bonds plus Federal Funds in the amount of $325,854.
Construction Contractor | Compass Engineering and Construction Services

Project Contact Information

Christi Tanner, PE
Office Phone | (505) 848-1523
Cell Phone | (505) 850-2041